How planners, lawyers, developers, utilities, regional development boards and land investors overlap across every data center fight in metro Detroit. Each community is fighting its own case. This page shows the threads between them.
Every case the planner map flags in the seven metro counties, plus watch rows for places tied to a case but not yet a case themselves. Developer names come from the developer tracker.
| Municipality | Planner / firm | Developer | Counsel | Regional and cross-site ties | Status |
|---|---|---|---|---|---|
| Allen Park CWA | Mike Auerbach, Carlisle/Wortman Associates | Solstice Data (CEO Phil Harvey) | City attorney: Joseph Couvreur. Solstice: Warner Norcross + Judd | UPDATED 2026-11-16: Council extended the moratorium six more months (unanimous, Nov 10). | Planning Commission DENIED 7-2 (Jun 4, 2026); city adopted 6-mo emergency moratorium (Jun 9, 2026, Ord. #04-2026E); moratorium ~expires Dec 2026. No new case activity found in Jul 22-Aug 21 sweep. |... | |
| Dearborn | David Breneau, In-House (City Staff) | Not named | NEW TO TRACKER (Sept 10, 30-day sweep). City Council advanced a 6-month freeze on new data-center development in early Sept 2026, joining a wave of nearly simultaneous local moratoriums statewide... | ||
| Detroit | Jill Bahm, Giffels Webster | Not named | NEW (Sept 10 sweep, Wayne Co. doc audit): City Council passed 6-2 resolution Mar 10 2026 urging a 2-year data-center moratorium; Mar 5 2026 CPC presentation confirmed zero current data-center zoning... | ||
| Gibraltar | Chuck Earl, McKenna Associates | CAL Realty, LLC and Raeden Acquisitions, LLC (Raeden co-founder/COO: Jason Green) | Plaintiffs: Honigman (CAL Realty), Bodman (Raeden) | Same federal judge as the Wixom suit (Robert J. White) | City moratorium passed Mar 9, 2026 (1-year blanket prohibition) |
| Huron Charter Township watch | Unknown | Not named | 2023 DRP finalist site (I-275 & Will Carleton); Aerotropolis board seat | WATCH (not a confirmed case): 2023 DRP study finalist site I-275 & Will Carleton (383 ac); Romulus CWA planner cited "Huron Township's moratorium" Dec 15, 2025 (unconfirmed); Aerotropolis board... | |
| Riverview watch | Jessa Sherrill, In-House (City Staff) | Not named | DUAL CWA ARRANGEMENT: Jessa Sherrill (City Planner, jsherrill@cityofriverview.com, 734-281-4242) is confirmed as an ACTIVE CWA employee placed at Riverview, she is not an independent in-house staffer... | ||
| Romulus CWA | John L. Enos, Carlisle/Wortman Associates | Not named | Aerotropolis board seat; CWA planner cited Huron Twp's moratorium | NEW (Sept 10 sweep, Wayne Co. doc audit): Dec 15 2025 PC minutes show unanimous recommendation for a data-center moratorium; Feb 4 2026 PC minutes note an upcoming board data-center seminar; Feb 18... | |
| Southgate watch | Joe Pezzotti, Carlisle/Wortman Associates | Not named | CWA CONFIRMED for Construction Code Services: Jennifer Dufore (Downriver Area Regional Manager) and Kevin Kendziora (Housing Inspector, listed as 'Housing Inspector - Southgate and Riverview') on CWA... | ||
| Sumpter Township CWA | Laura Kreps, Carlisle/Wortman Associates | Not named | Joint PC with Van Buren Twp (Project Cannoli) and Belleville | As of July 2026 joint PC meeting (Van Buren Twp / Belleville / Sumpter): township working on a data center moratorium while planners draft ordinance language. Matthew Oddy provided updates on behalf... | |
| Trenton | Elizabeth Gunden, Beckett & Raeder | Not named | NEW 2026-09-10 (a resident's own primary-source pull -- Trenton Sept 8, 2026 Regular Council Meeting minutes/packet): resident Denise Gerlica raised data-center concerns during public comment,... | ||
| Van Buren Township | Dan Power, In-House (City Staff) | Panattoni (developer) | Aerotropolis board chair seat; DTE contracts approved by MPSC (U-22058); 2023 DRP study rated a separate Van Buren parcel; joint PC with Sumpter (CWA) and Belleville | Feb 11 & May 13, 2026 PC presentations; May 19, 2026 Board of Trustees presentation; Development Agreement signed May 20, 2026. Joint PC with City of Belleville and Sumpter Township. | OCT 5: Wayne... |
| Municipality | Planner / firm | Developer | Counsel | Regional and cross-site ties | Status |
|---|---|---|---|---|---|
| Ann Arbor Township CWA | Sally M. Elmiger, Carlisle/Wortman Associates | Not named | UPDATED 2026-08-04: Board passed a 12-month moratorium on new data center development Feb 16, 2026, purely precautionary (Supervisor Diane O'Connell: 'No one has approached township officials... | ||
| Augusta Township CWA | Joe Pezzotti, Carlisle/Wortman Associates | Thor Equities (with Form8tion) | Water from YCUA, which has a 12-month data center moratorium | Rezoning approved Jul 2025; referendum on Ord. 2025-02 (Aug 2026 ballot) | |
| Bridgewater Township | Unknown | Not named | Part of the Related Digital acreage next to Saline Twp | Related Digital's proposed data center reportedly spans ~500 acres within Bridgewater Township (plus 575 acres in adjacent Saline Township, already tracked as our core case). Saline Township's board... | |
| Dexter Township CWA | Megan Masson-Minock / Grayson Moore (consultants) / Fletcher Reyher, AICP (in-house Director), Carlisle/Wortman Associates | Not named | UPDATED (Aug 21 sweep): a full Data Center Ordinance draft (dated Jul 14, 2026) is under active review as of a Jul 28, 2026 PC packet, with Foster Swift legal redlines and OHM Advisors engineering... | ||
| Freedom Township | Rodney Nanney / Jim Coval, Unknown | Not named in memory, STILL UNRESOLVED after a dedicated Aug 21 sweep search | Township drafting an "AI/Data Center Ordinance" as of Jun 2026. No new coverage found on ordinance progress in the Aug 21 sweep. | ||
| Lodi Township | Hannah Smith, CIB Planning | Not named | Adjacent to the Saline Twp Stargate campus | Lodi Township enacted Data Center Ordinance 2026-001, proactive data center zoning regulation in response to proximity to the Saline Township Oracle/OpenAI Stargate campus (~5 miles southwest).... | |
| Manchester Township watch | Alissa Starling, Carlisle/Wortman Associates | Not named | CHECKED 2026-08-04: no data-center/HRDF activity found across every Township Board meeting reported Jun 2025-May 2026 (contemporaneous local-paper coverage reviewed). A Feb 2026 WKAR statewide... | ||
| Pittsfield Township CWA | Benjamin R. Carlisle, Carlisle/Wortman Associates | Not named | FLAG, POSSIBLE STATUS CONFLICT (Aug 21 sweep): an Aug 6, 2026 WEMU article describes the township as still under a moratorium with the ordinance "still being refined," and covers a PC public-input... | ||
| Salem Township CWA | Stephen Zampardo / Paul Montagno (CWA), Carlisle/Wortman Associates | Key Capture Energy (KCE) | PC approved 5-2 Jul 20, 2026 with $200k + $100k/yr host community agreement; HRDF ordinance still in discussion | ||
| Saline CWA | Benjamin R. Carlisle, Carlisle/Wortman Associates | Not named | Moratorium only (Jan 2026); no ordinance text drafted. RECONFIRMED in the Aug 21 sweep, no coverage found past January 2026. | ||
| Saline Township CWA | Mike Auerbach, Carlisle/Wortman Associates | RD Michigan Property Owner I LLC (presented publicly as "Related Digital"; agent James Kraus) | Developer: Alan Greene, Dykema Gossett. Township litigation counsel: David Landry | DTE power contracts challenged by AG Nessel; Related Digital paid Manchester Twp fire dept $500,000 | UPDATED 2026-11-16: Trustees reaffirmed the 12-year, 50% abatement and moved to establish the Industrial Development District. | PC voted 5-2 NOT to rezone (Aug 12, 2025); Township Board voted 4-1 to DENY rezoning (Sep 10, 2025); consent judgment entered Oct 15, 2025 overriding the denial. CORRECTED (Aug 21 sweep, reconciled... |
| Scio Township CWA | Laura K. Kreps, Carlisle/Wortman Associates | Not named | RESOLVED 2026-08-04 (afternoon): full primary-source drafting history obtained from PC/BOT packets a resident downloaded directly. CONFIRMED (not circumstantial): CWA planner Laura Kreps introduced a... | ||
| Sylvan Township | Scott Pacheco, AICP, SP Urban Planning Service | Not named | |||
| York Township | Greg Elliott, Greg Elliott P.L.C. | Sansone Group | Sansone Group, same developer partner as the Wixom lawsuit | WITHDRAWN: purchase agreement withdrawn Apr 2026 after township refused to amend agreement/rezone research park to heavy industry | |
| Ypsilanti | Josh Burns, In-House (City Staff) | Not named | NEW 2026-09-10 (sweep): distinct from Ypsilanti Charter Township (id 8), this is the City of Ypsilanti's OWN separate data-center fight. City Council passed a first reading of a 60-day emergency... | ||
| Ypsilanti Township CWA | Benjamin R. Carlisle, Carlisle/Wortman Associates | University of Michigan | YCUA 12-month moratorium (Apr 2026); UM state zoning exemption | UM AFFIRMED Textile Road as its selected site Aug 11, 2026 (Detroit News/Michigan Public, Aug 12); town hall scheduled Sep 9, 2026 |
| Municipality | Planner / firm | Developer | Counsel | Regional and cross-site ties | Status |
|---|---|---|---|---|---|
| Bedford Charter Township watch | Unknown | Not named | Not individually researched this pass. Calhoun County's Community Development/Planning department provides review/coordination support to townships but does not itself administer zoning or issue... | ||
| Berlin Charter Township CWA | Laura Kreps, Carlisle/Wortman Associates | Microsoft | Dykema Gossett letter to PC (May 2026) | Moratorium extended to Nov 2026; ordinance draft in an attorney-directed "holding pattern" awaiting an MTA template as of Jul 2026. No new coverage found in the Aug 21 sweep, ordinance status, the 3... | |
| Dundee (Village) CWA | Mike Auerbach (land use) and Megan Masson-Minock (engagement), Carlisle/Wortman Associates, Master Plan update | Not named | Auerbach's third confirmed municipality with Allen Park and (formerly) Saline Twp; neighbors Dundee Twp (Cloverleaf, Project Ironwood) | UPDATE 2026-10-21: updated Master Plan reported adopted Oct 20, 2026 (minutes not yet posted). July 2026 land-use draft had no data-center language; final adopted text not yet reviewed. Earlier "no CWA connection" note superseded. | |
| Dundee Township | Lucie Fortin, The Mannik & Smith Group | Cloverleaf Infrastructure (a land-preparer; hands off to an end-user/operator not yet named) | Township: Fahey Schultz Burzych Rhodes | Cloverleaf Infrastructure (Project Ironwood); planner Fortin also serves Bedford Twp | Moratorium enacted Oct 14, 2025, renewed Dec 9, 2025 (180 days). Developer identity GAP RESOLVED in the Aug 21 sweep (was previously unknown). No confirmation found on whether the Dec 9 renewal has... |
| Erie Township | Spicer Group | Not named | 2023 DRP site submission (LAC, with Bedford Twp) | 1-year moratorium (Ord. 132, Feb 2026); draft ordinance delivered Jul 21, 2026. No adoption vote found in Aug 21 sweep, township's own site still shows the Feb 10 moratorium post as the latest item. | |
| Frenchtown Charter Township | Kristin Hatfield, OHM Advisors | Cloverleaf Infrastructure | Cloverleaf Infrastructure (Project Cherry Blossom) | Early-stage -- land must be sold/rezoned before it can advance, per Township Clerk Kyle Bryant. Public informational meeting held; first reported Nov 2025, still active as of Mar 2026 Planet Detroit... |
| Municipality | Planner / firm | Developer | Counsel | Regional and cross-site ties | Status |
|---|---|---|---|---|---|
| Brighton Township | Kelly Mathews, In-House (City Staff) | Not named | NEW 2026-10-05: Township adopted a moratorium on data center development while the Planning Commission drafts an ordinance (Livingston Daily, Sept 24, 2026). Joins Genoa, Howell, Green Oak, Tyrone... | ||
| Genoa Township | Kelly VanMarter, In-House (City Staff) | Not named | Township attorney: Joe Seward | 2023 DRP finalist site (Latson Rd) | UPDATED (Aug 21 sweep, Aug 18): Board voted to EXTEND the moratorium another 6 months, explicitly to finish a noise study after a resident sound engineer flagged low-frequency/hum concerns in the... |
| Green Oak Township CWA | Paul Montagno / Michelle Marin, Carlisle/Wortman Associates | Not named | UPDATED (Aug 21 sweep, Jul 13): Board ADOPTED a "High Resource Demand Facilities Overlay District" designating 6 specific low-impact parcels (incl. near the prison); also moving toward an NDA ban,... | ||
| Handy Township watch | Bonnie Flanery, In-House (City Staff) | Not named | Adjacent to Howell Township (id276, already in our map), the epicenter of a ~1,000-acre data center rezoning proposal (Stantec Consulting/Randee LLC) that Howell's planners rejected; Howell passed a... | ||
| Howell Township CWA | Paul Montagno / Brady Heath, Carlisle/Wortman Associates | Randee LLC (filing entity); developer widely reported as META (per Data Center Dynamics) | Stantec (developer's engineer); next to Handy Twp, a 2023 DRP submission. Ordinance purpose section drawn from Green Oak's CWA HRDF ordinance (same CWA principal, Montagno); CWA cited Howell's draft as sample language at Dexter Twp | UPDATED 2026-11-16: CORRECTED, the planner is CWA. CWA-drafted High Impact Land Use overlay, heavily edited by the Resident Research Committee; PC hearing Nov 17. The Nov 16 hearing draft cut setbacks from 1,500 to 2,640 ft (March draft) to 200 ft from the overlay edge and dropped the 25% renewable minimum; an NDA-ban ordinance is being drafted. Moratorium runs to about late May 2027. Earlier: REJECTED by PC Sep 2025; developer WITHDREW Dec 2025. | |
| Pinckney | Lucie Fortin, Unknown | Not named | Same "Section 12:22 Data Centers" language under PC review (May 2026). No new coverage found in Aug 21 sweep. | ||
| Putnam Township CWA | Joe Pezzotti, Carlisle/Wortman Associates | Not named | Drafting ordinance + "Moratorium for Emerging Land Uses"; hearing-ready as of May 2026. No new coverage found in Aug 21 sweep (township/county packet pages not accessible via search). | ||
| Tyrone Township | Mario Ortega, AICP, McKenna Associates | Not named | Moratorium passed Dec 10, 2025, renewed May 24, 2026. NEW (Aug 21 sweep, Jul 9): a resident publicly pressed officials on whether they'd signed NDAs with private parties over data centers; officials... | ||
| Unadilla Township CWA | John L. Enos, Carlisle/Wortman Associates | Not named | Draft zoning rewrite adds "Section 12:22 Data Centers" (Mar 2026). No new coverage found in Aug 21 sweep. |
| Municipality | Planner / firm | Developer | Counsel | Regional and cross-site ties | Status |
|---|---|---|---|---|---|
| Brandon Township CWA | Jason Wilton, Carlisle/Wortman Associates | Not named | UPDATED 2026-10-29: 180-day moratorium (Res. 424-26, May 4) extended 180 days on Sept 14 (Res. 435-26) to ~Mar 13, 2027; no ordinance draft released yet. CWA planner Masson-Minock told the PC in Jan 2026 her firm has a data-center model ordinance; the extension cites the new MTA model ordinance... | ||
| Commerce Township | David Campbell, In-House (City Staff) | Not named | NEW 2026-08-20: Township Board adopted a 6-month data center moratorium Feb 2026 (originally set to expire ~Aug 2026; per the July 2026 Planning Dept monthly report, staff expected the Board to... | ||
| Groveland Township | Danielle Willcock, In-House (City Staff) | Not named | Sheena land network holds Groveland Real Properties LLC (unproven link to courting developers) | CORRECTED 2026-09-13 (Oakland County completeness research): the previously-noted Tri-County Times "data-center moratorium" claim for Groveland Township traces to an article actually about Tyrone... | |
| Holly Township | Alexis Farrell, McKenna Associates | Not named | 180-day moratorium Feb 2026, renewed Jul 2026. No independent confirmation source found for the July renewal or further ordinance progress in Aug 21 sweep. | ||
| Independence Township CWA | Carlisle/Wortman Associates, Carlisle/Wortman Associates | Not named | CONFIRMED 2026-09-13 (Oakland County completeness research, NEW CWA client discovery): Carlisle/Wortman Associates is the Township's current planning consultant. The Township Board approved a 6-month... | ||
| Lyon Township | Patrick Sloan, McKenna Associates | Verrus | Township: Rosati Schultz Joppich & Amtsbuechler | Project had PRELIMINARY APPROVAL before the township's moratorium (~Dec 2025); 6-mo moratorium on NEW projects passed Mar 2, 2026 (does not affect Verrus's already-approved project) | |
| Oakland Township | Donald Mende, In-House (City Staff) | Not named | |||
| Oxford Township CWA | Matteo Passalacqua, Carlisle/Wortman Associates | Not named | CWA's Passalacqua also drafted Wixom's ordinance | NEW TO TRACKER (Sept 10, 2026 -- a resident live at the meeting). Township already has a 1-year data-center moratorium in place, expiring Feb 2027; Sept 10, 2026 PC first reading moved to adopt a... | |
| Pontiac | Amy Bavin, In-House (City Staff) | Not named | NEW 2026-09-13: Pontiac adopted a 6-month data center moratorium Jan 21, 2026 (confirmed by Detroit News and the statewide datacenterbans.com tracker, which as of Sept 7, 2026 still lists it... | ||
| Rochester Hills | Sara Roediger, AICP, In-House (City Staff) | Not named | Moratorium extension CONFIRMED passed Aug 10-11, 2026, pushes through ~mid-March 2027 | ||
| Southfield | Terry Croad, AICP, ASLA, In-House (City Staff) | Not named | NEW (2026-08-19, cross-referenced from MLive's statewide data center tracking map): developer Metrobloks proposed a 100-megawatt data center on a vacant parcel near I-696. Status: Pending, Southfield... | ||
| Springfield Township CWA | Megan Masson-Minock, Carlisle/Wortman Associates | Pre-application via Cushman & Wakefield/Sevenich; land held by 84 Andersonville LLC (Sheena family) | Sheena land network (84 Andersonville LLC); possible tie to Groveland Twp | CWA ordinance draft (Jun 15, 2026 memo: "our firm's working model") | |
| Wixom CWA | Benjamin R. Carlisle, Carlisle/Wortman Associates | Wixom Industrial One LLC (Dennis Griffin, Pleasant Ridge developer) | City: Rosati Schultz Joppich & Amtsbuechler | Developer partner Sansone Group also pursued York Twp; same federal judge as Gibraltar | OCT 5: Ordinance No. 2026-01 ADOPTED Aug 25, 2026 (setback cut 2,640 ft to 1,500 ft; Table 2 ambient standard deleted); moratorium expired Sept 24, 2026. | prior: 6-mo moratorium (Mar 2026, expires... |
| Municipality | Planner / firm | Developer | Counsel | Regional and cross-site ties | Status |
|---|---|---|---|---|---|
| Armada Township | Michelle Bailey, In-House (City Staff) | Not named | 180-day moratorium (Res. 2026-02), adopted Jan 14, 2026, window would lapse ~mid-July 2026; no renewal vote or expiration news found in Aug 21 sweep | ||
| Lenox Township CWA | Shana Lengyel, Carlisle/Wortman Associates | Lenox and Chesterfield Economic Development Alliance LLC (rezoning applicant, Nov 2026; end use not stated) | Cloverleaf Infrastructure, also at Dundee Twp and Frenchtown Twp | UPDATED 2026-11-22: Nov 16 hearing CONFIRMED CANCELLED by a court restraining order (notice defect lawsuit); new Dec 4, 2026 Special PC meeting posted (unconfirmed as the reschedule); separate HRDF ordinance (Sec. 719.744) on the Nov 23, 2026 regular PC agenda. | UPDATED 2026-11-16: Rezoning hearing Nov 16 on about 1,402 acres; MLive says the applicant's attorneys earlier described a data center campus. | No formal application or named developer. Sept 3-4, 2026: New Haven Village President Brian Meissen's FOIA request surfaced Jan 2026 emails showing a property owner told the Supervisor 'we have been... | |
| Sterling Heights | Jake Parcell, Ph.D, In-House (City Staff) | Not named | NEW 2026-10-05: City has a data center moratorium in place and held a resident open house on it Sept 28, 2026 (presentation plus panel). No named developer found. | ||
| Washington Township | Dana Berschback, In-House (City Staff) | Not named | An earlier applicant WITHDREW its application (~May 19, 2026); board then passed a 6-month moratorium (~May 23, 2026); ordinance still under development, water/sewer capacity as key restriction. No... |
| Municipality | Planner / firm | Developer | Counsel | Regional and cross-site ties | Status |
|---|---|---|---|---|---|
| Kimball Township watch | Unknown | Not named | Site is JS-rendered; nav/subpages couldn't be extracted. | COORDINATE CORRECTED 2026-09-11 (statewide close-pair audit): moved to Wikipedia infobox township centroid. | WATCH 2026-10-05: 4730 Smiths... | ||
| Port Huron Township | Steve Cassin, Cassin Planning Group | Not named | Cassin Planning Group (CWA alumnus); 'high resource-demand facilities' moratorium wording | NEW 2026-10-05: Township board unanimously adopted a moratorium of up to 12 months (with an option to extend) on new applications for data centers and other 'high resource-demand facilities' while it... |
CWA/Carlisle-Wortman staff (Auerbach, Kreps, Masson-Minock, Lengyel, Passalacqua, Enos, Carlisle) are the planning firm on 22 of the 54 metro Detroit data center cases on the map, with different people at each site, not one individual.
Billing records show Allen Park's own planner on a call with Saline's litigation counsel the exact day Saline's board approved the settlement overriding its own denial.
A rezoning review citing an ordinance provision that was never actually adopted let an application proceed that the township's real rules should have rejected outright.
A June 2026 memo to Springfield Township's Planning Commission states the ordinance draft is built on "our firm's working model."
Dykema Gossett represented the developer in Saline and later appeared at Berlin (a CWA site) on behalf of Microsoft; one Dykema attorney has a prior working relationship with a CWA principal.
A detailed, resident-committee-authored "HEID" ordinance for Washington Township is moving between other townships' planning processes independent of any official consultant network.
A broker told Allen Park's DDA director 14 months early; Project Flex's earliest site plan reached Oakland County's airport office 5 weeks before Lyon Township itself saw anything public.
Allen Park's Mayor privately sought to correct an inflated tax figure with no public follow-through; Washington Township's Supervisor's private enthusiasm didn't match his public "exploratory" framing.
A senior planner told the developer the site was industrial-compatible; the township's own land-use map says otherwise.
A disputed $6.2M pitch, a $43.1B abatement-valuation fight, and an untested $24M/30-year TIF projection, same underlying vulnerability, three different points in the process.
Officials publicly denied developer contact in January 2026, a denial the township's own FOIA'd emails contradict, leading to recall petitions against four of five trustees.
Three separate mechanisms: a rebranded team (Allen Park, from Sabre56/Next Grid to Solstice), one developer under several project names (Cloverleaf Infrastructure as Project Ironwood in Dundee Twp, Project Cherry Blossom in Frenchtown Twp, and Project Honeycomb/EcoPower in Lenox Twp), and the same land pitched for two different uses (Washington Township).
A single Oakland County land investor holds a confirmed parcel at one site and has a plausible, unproven presence at a neighboring one, legal, ordinary land investing, worth watching.
A legally-grounded privilege claim, an implausible "no records" response, and an outright omission of a known meeting, three sites, three ways the first FOIA answer wasn't the complete one.
After a withdrawal, after a lawsuit, and before any application at all, three townships converge on the same defensive move: hire outside technical consultants and write a standards-based ordinance.
In 2023 the Detroit Regional Partnership asked local economic development and utility partners to submit hyperscale data center sites. Genoa's Latson Rd site was a finalist, cited for "community receptivity" and "appropriate zoning." Genoa and Erie both adopted moratoriums in Feb 2026. Who submitted each site is the open question.
On Mar 5, 2026 the Aerotropolis board, chaired from Van Buren Twp, heard a DTE presentation on data center developments. Van Buren's Project Cannoli development agreement followed 11 weeks later.
Sansone Group backs Wixom Industrial One, now suing Wixom, and separately pursued a 1 GW campus on former Toyota land in York Twp until April 2026. This corrects the earlier finding that no developer is shared across tracked sites.
Wixom Industrial One v. Wixom (2:26-cv-12754) and CAL Realty/Raeden v. Gibraltar (2:26-cv-12893) are both assigned to Judge Robert J. White, E.D. Mich. A ruling on Wixom's mootness argument will shape Gibraltar's case and any future Solstice suit.
Matteo Passalacqua drafted Wixom's ordinance, which lost its enforcement provisions in an Aug 3 legal-review revision before adoption. He is also CWA's planner at Oxford Twp, where about 350 people turned out Sept 10.
CWA staff serve as Riverview's community development director and city planner, and CWA's Construction Code Services handles building and housing inspection in Southgate, Riverview, Pittsfield Twp and on Ann Arbor projects including Google's headquarters.
Van Buren, Sumpter and Belleville share a joint Planning Commission. Sumpter's planner is CWA's Laura Kreps, so CWA staff sit on the body that sees Van Buren-area items.
Port Huron Twp's Sept 2026 moratorium covers data centers and other "high resource-demand facilities," the same term CWA's template uses. Its planner is Cassin Planning Group. This reopens the Cassin lead that was closed Sept 5; the moratorium text has not yet been read.
Rosati Schultz Joppich & Amtsbuechler represents Wixom in the federal suit and is Lyon Twp's counsel during Project Flex. Noted for awareness only, not as evidence of impropriety.
Dead ends stay on the record so the method is visible. This section replaces the former Steve Cassin watch page.
Checked Sept 5, 2026: CWA alumnus (joined CWA Jun 23, 2017). No shared municipality, document, or billing record with Mike Auerbach. Confirmed clients Port Huron Twp and Casco Twp showed no data center activity. REOPENED Oct 5, 2026: Port Huron Twp has since adopted a moratorium using CWA's "high resource-demand facilities" wording (see pattern above).
In-house planner (city) and a volunteer-chaired PC (township). No Cassin link and no data center activity found.
Real data center fight (Prologis, withdrawn May 2026), but the planner is in-house and the Master Plan is a Giffels Webster product. No Cassin connection.
A reported Troy data center moratorium traced to Troy, Illinois. Troy, Michigan remains a no-activity control case.
A commercial storage zoning amendment, not a data center ordinance.
An early record named Stephen Cassin as Lenox's planner. Lenox's CWA planner is Shana Lengyel; corrected Aug 4, 2026.